Utility-Scale Solar Energy Generation Facility

21K

Equivalent to powering 21,000 Oklahoma homes annually

100 MW

Located adjacent to the town of Snyder / Kiowa County, Oklahoma

2025

Commercial operation date

Solar-panel

The Project

Kiowa County Solar Projects is Savion’s first to be developed, constructed, and owned by Savion in Oklahoma. Beginning its journey in 2017 and obtaining a generation interconnection agreement in 2022, construction on the project lasted from August 2023 to December 2024. Kiowa interconnects into the AEP substation and connects to the Southwest Power Pool as it quietly generates renewable energy during its 40-year lifespan.

Agrivoltaics

Kiowa has an agreement with Between the Rows (BTR) to partner with local farmers outside the project’s fence.

Solar-panel

189,921 bifacial solar panels

Trackers

Single-axis trackers

Inverters

31 Inverters